Thank you, Mr. Chair.
Thank you, Minister and folks, for coming here today. I appreciate it.
In one of his questions, Mr. Alghabra talked about your November 1 memo in which you were provided with three options. I'm comforted to see that at least the management oversight gave you options to look at it, even though there's a recommendation. You made the comment that we might be looking a number of years out before this could ever be done.
The Auditor General, in her remarks of September 5, 2007, on the special examination, said that the estimate at that point in time was for probably around $130 million to complete the two reactors, one of which would be done in 2008 and one in 2009.
Given that consideration, what kinds of estimates did you foresee that it would have taken—just a ball park range—to finish these if you went ahead?