Allow me to clarify a few things. For example, at paragraph 6 of the special examination, we mention that we did not do any technical assessment of the safety and security of the facilities because that work is done by the regulatory Commission. Therefore, we rely on the assessment of a third-party that is independent from the corporation.
Those people have to be satisfied and we rely on their opinion. For example, on the issue of waste management, they had approved the plan of the corporation. We did not want to start verifying that because we are not experts in nuclear waste management. As far as the MAPLE project is concerned, they said that the corporation did not meet the requirements and that they were not satisfied. There again, we relied on them and, through discussions with the corporation, we tried to assess the seriousness of the situation. In any case, we do not carry out our own technical assessment of the facilities.