Okay, thank you. That's important, because of course when you reported to the committee in June we certainly weren't hearing anything about this not being completed until March, which this diagram suggests. I would certainly be concerned if this had been presented to CNSC in June, when we were still hearing about it being three months, possibly longer, but nothing like this. So that's good to hear, if that's the case.
The chart indicates that by October you should have final confirmation of the extent of repair, have the corrosion mechanism determined, and begin full-scale mock-up testing of the repair tool and by the end of the month initiate repair of the vessel. Is that what you're doing?